New bridge, road work scheduled on County Road 3

County Road 3 near Minneota will get a new bridge and road work this summer.

Tuesday the Lyon County Board approved replacement of a timber bridge over the Yellow Medicine River and road construction about 4.4 miles north of Minneota on County Road 3.

Bituminous surfacing will take place next year as a separate contract. The start date of the project is July 9 and the completion date is October 20 and funding for the project is 100 percent state aid. Work will be done by R&G Construction Co. of Marshall at a cost of $1,722,108.63.

“The bid came in 17 percent under our estimate,” said Lyon County Engineer Aaron VanMoer.

IN OTHER action the board:

•For security reasons, changed the Lyon County Government Center hours to: Open at 7:30 a.m. and closed at 5 p.m., Monday through Friday. Currently, the center hours have been 6 a.m. to 6 p.m., Monday through Friday.

“Being open without a lot of staff here is inviting trouble,” said Lyon County Administrator Loren Stomberg. Accommodations will be made for special needs.

“We can make it work,” said Stomberg. •Approved a Conditional Use Permit to Chad Louwagie for an addition to an existing monoslope cattle shed located on County Road 22, Cottonwood.

The existing building is 100 feet by 240 feet. The proposed addition is approximately 140x100 feet along with a 40-foot lean.

The Lyon County Planning and Zoning Committee approved the addition that will double the cattle heard from 400 head to 800 head.